Bạn đang xem bản rút gọn của tài liệu. Xem và tải ngay bản đầy đủ của tài liệu tại đây (20.05 MB, 681 trang )
www.downloadslide.net
Chapter 7 Managing Risk 239
Carlos: Bill, I am aware of the problem. The PMI Roundtables I attend also talk to the
difficulty of keeping teams and other stakeholders willing to revisit risk once the project is on its way. [PMI Roundtables are monthly meetings of practicing PMs across
industries designed to address project management problems.] I also heard war stories
at a recent project management roundtable meeting. I have some notes from the meeting right here.
It all started with the leader’s question: “How many project managers actually manage risk over the complete project life cycle?”
PM 1: We all work through the risk management process well before the project
begins. We have the process template of risk identification, assessment, response,
control, risk register, and contingency down pat. We just don’t follow through after
the project begins. I think interest dies. Have you ever tried to get project stakeholders to come to a risk meeting when the project is moving relatively well?
PM 2: A recent e-mail from one of our stakeholders said, “We’ll deal with it [risk]
when it happens.”
PM 3: I agree. Interest seems to move from future oriented to reactionary. Also,
risk management seems to degenerate into issue (concerns and problems) management versus real risk management.
PM 4: I ask team members, “What is the risk of not managing risk over the life of
the project?” Sometimes this question nudges a few to respond positively, especially if risks have changed or new ones are perceived. I use a failed project where
a solid risk management process would have avoided the project failure. I explain
all of the risk management processes that would have helped to improve the risk
elements—risk identification, triggers, responsibility, transfer, accept, etc.
PM 5: Risk is not a line item in the budget or schedule. Maybe it is in the contingency budget to cover “unknowns of unknowns.” I have to watch that management
doesn’t try to squeeze out the contingency budget for something else.
Carlos continued to share with his boss that there were many more comments, but very
few gave much guidance. Carlos then shared his idea:
Carlos: Colette is our best trainer, especially in transition management, and she would
be a great choice for following through on this problem. Her training classes on upfront
risk management are excellent. Should we ask her to present a session?
Bill: You are right, Carlos, Colette is ideal. She is smart and a great team motivator.
Ask her, but give her some kind of direction for focus.
A few days later, Carlos sent out a memo:
Colette, this is to follow up on our lunch conversation yesterday discussing sustaining
risk management after the project is on its way. Given the nature of our futuristic company, we should stress the point that our product development projects carry many
more inherent risks than do traditional projects. I suggest the training classes should
drill down on concrete actions and policies that will encourage interest of team members and other project stakeholders in sustaining risk management practices during
project execution.
Colette, we appreciate your taking on this project. When you have developed your
training session, please give me a copy so I can schedule and support your efforts.
Regards, Carlos
www.downloadslide.net
240 Chapter 7 Managing Risk
CHALLENGE
Divide the class into teams of three or more participants.
Colette needs your help to develop her training program. You may wish to consider
the questions listed below to initiate ideas.
∙ Why do project stakeholders lose interest in project risk after the project is under
way?
∙ What are the dangers of not keeping on top of risk management during
implementation?
∙ What kind of business is Futuronics in?
Brainstorm specific actions that will encourage project stakeholders to continue to
scan and track the project environment for risk events. Suggest three concrete actions
or scenarios that will encourage project stakeholders to change their behavior and truly
support risk management while projects are being implemented. The following outline
headings may be helpful in developing possible actions that would improve/enhance
stakeholder support.
∙ Improving the risk management process
∙ Organization actions
∙ Motivating participation
Appendix 7.1
PERT and PERT Simulation
LEARNING OBJECTIVES
After reading this appendix you should be able to:
A7-1 Calculate basic Pert Simulation projections.
PERT—PROGRAM EVALUATION AND REVIEW TECHNIQUE
LO A7-1
Calculate basic Pert
Simulation projections.
In 1958 the Special Office of the Navy and the Booze, Allen, and Hamilton consulting
firm developed PERT (program evaluation and review technique) to schedule the more
than 3,300 contractors of the Polaris submarine project and to cover uncertainty of
activity time estimates.
PERT is almost identical to the critical path method (CPM) technique except it
assumes each activity duration has a range that follows a statistical distribution. PERT
uses three time estimates for each activity. Basically, this means each activity duration
can range from an optimistic time to a pessimistic time, and a weighted average can be
computed for each activity. Because project activities usually represent work, and
because work tends to stay behind once it gets behind, the PERT developers chose an
approximation of the beta distribution to represent activity durations. This distribution
is known to be flexible and can accommodate empirical data that do not follow a normal distribution. The activity durations can be skewed more toward the high or low
end of the data range. Figure A7.1A depicts a beta distribution for activity durations
that is skewed toward the right and is representative of work that tends to stay late once
it is behind. The distribution for the project duration is represented by a normal
www.downloadslide.net
Chapter 7 Managing Risk 241
FIGURE A7.1 Activity and Project Frequency Distributions
PROJECT
ACTIVITY
a
m
b
TE
(A)
(B)
(symmetrical) distribution shown in Figure A7.1B. The project distribution represents
the sum of the weighted averages of the activities on the critical path(s).
Knowing the weighted average and variances for each activity allows the project
planner to compute the probability of meeting different project durations. Follow the
steps described in the hypothetical example given next. (The jargon is difficult for
those not familiar with statistics, but the process is relatively simple after working
through a couple of examples.)
The weighted average activity time is computed by the following formula:
te =
a + 4m + b
6
(7.1)
where
te = weighted average activity time
a = optimistic activity time (1 chance in 100 of completing the activity
earlier under normal conditions)
b = pessimistic activity time (1 chance in 100 of completing the activity
later under normal conditions)
m = most likely activity time
When the three time estimates have been specified, this equation is used to compute
the weighted average duration for each activity. The average (deterministic) value is
placed on the project network as in the CPM method and the early, late, slack, and
project completion times are computed as they are in the CPM method.
The variability in the activity time estimates is approximated by the following equations: Equation 7.2 represents the standard deviation for the activity. Equation 7.3 represents the standard deviation for the project. Note the standard deviation of the
activity is squared in this equation; this is also called variance. This sum includes only
activities on the critical path(s) or path being reviewed.
b−a
σt = (
e
6 )
(7.2)
σT = √ Σσ2t
(7.3)
E
e
Finally, the average project duration (TE) is the sum of all the average activity times
along the critical path (sum of te), and it follows a normal distribution.
www.downloadslide.net
242 Chapter 7 Managing Risk
Knowing the average project duration and the variances of activities allows the
probability of completing the project (or segment of the project) by a specific time to
be computed using standard statistical tables. The equation below (Equation 7.4) is
used to compute the “Z” value found in statistical tables (Z = number of standard
deviations from the mean), which, in turn, tells the probability of completing the project in the time specified.
Z=
TS − TE
(7.4)
√ Σσ2
te
where
TE = critical path duration
TS = scheduled project duration
Z = probability (of meeting scheduled duration) found in statistical Table A7.2
A HYPOTHETICAL EXAMPLE USING THE PERT TECHNIQUE
The activity times and variances are given in Table A7.1. The project network is presented
in Figure A7.2. This figure shows the project network as AOA and AON. The AON network is presented as a reminder that PERT can use AON networks as well as AOA.
The expected project duration (TE) is 64 time units; the critical path is 1-2-3-5-6.
With this information, the probability of completing the project by a specific date can
easily be computed using standard statistical methods. For example, what is the probability the project will be completed before a scheduled time (TS) of 67? The normal
curve for the project would appear as shown in Figure A7.3.
Using the formula for the Z value, the probability can be computed as follows:
Z=
TS − TE
√ Σσ2
te
=
67 − 64
√25 + 9 + 1 + 1
=
+3
√36
= +0.50
P = 0.69
Reading from Table A7.2, a Z value of +0.5 gives a probability of 0.69, which is interpreted to mean there is a 69 percent chance of completing the project on or before 67
time units.
TABLE A7.1
Activity Times and
Variances
Activity
a
m
b
te
[(b – a)/6]2
1–2
2–3
2–4
3–5
4–5
5–6
17
6
16
13
2
2
29
12
19
16
5
5
47
24
28
19
14
8
30
13
20
16
6
5
25
9
4
1
4
1
www.downloadslide.net
Chapter 7 Managing Risk 243
FIGURE A7.2
3
Hypothetical
Network
AOA Network
13
30
1
16
59
56
2
20
5
5
6
6
TE = 64
4
AON Network
0
30 B 43
43 D 59
13
16
59 F 64
A 30
59
56
30
30 C 50
50 E 56
20
6
5 64
TE = 64
Conversely, the probability of completing the project by time period 60 is computed
as follows:
Z=
=
60 − 64
√25 + 9 + 1 + 1
−4
√36
= −0.67
P ≈ 0.26
FIGURE A7.3
Possible Project
Durations
TS = 67
TE = 64
www.downloadslide.net
244 Chapter 7 Managing Risk
TABLE A7.2
Z Values and
Probabilities
Z Value
Probability
Z Value
Probability
.001
.003
.005
.008
.014
.023
.036
.055
.081
.115
.159
.212
.274
.345
.421
+0.0
+0.2
+0.4
+0.6
+0.8
+1.0
+1.2
+1.4
+1.6
+1.8
+2.0
+2.2
+2.4
+2.6
+2.8
.500
.579
.655
.726
.788
.841
.885
.919
.945
.964
.977
.986
.992
.995
.997
−3.0
−2.8
−2.6
−2.4
−2.2
−2.0
−1.8
−1.6
−1.4
−1.2
−1.0
−0.8
−0.6
−0.4
−0.2
From Table A7.2, a Z value of −0.67 gives an approximate probability of 0.26, which
is interpreted to mean there is about a 26 percent chance of completing the project on
or before 60 time units. Note that this same type of calculation can be made for any
path or segment of a path in the network.
When such probabilities are available to management, trade-off decisions can be
made to accept or reduce the risk associated with a particular project duration. For
example, if the project manager wishes to improve the chances of completing the project by 64 time units, at least two choices are available. First, management can spend
money up front to change conditions that will reduce the duration of one or more
activities on the critical path. A more prudent, second alternative would be to allocate
money to a contingency fund and wait to see how the project is progressing as it is
implemented.
EXERCISES
1. Given the project information below, what is the probability of completing the
National Holiday Toy project in 93 time units?
Act. ID
1
2
3
4
5
6
7
Description
Predecessor
Optm. (a)
Most likely (m)
Pess. (b)
Design package
Design product
Build package
Secure patent
Build product
Paint
Test market
None
1
1
2
2
3, 4, 5
6
6
16
4
24
17
4
13
12
19
7
27
29
7
16
24
28
10
36
47
10
19
Act time te
Variance [(b − a)/6]2
Critical
2. The Global Tea and Organic Juice companies have merged.
The following information has been collected for the “Consolidation Project.”
www.downloadslide.net
Chapter 7 Managing Risk 245
Activity
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
1.
2.
3.
4.
5.
Description
Predecessor
a opt
m ml
b pess
Codify accounts
File articles of unification
Unify price and credit policy
Unify personnel policies
Unify data processing
Train accounting staff
Pilot run data processing
Calculate P & L and balance sheet
Transfer real property
Train salesforce
Negotiate with unions
Determine capital needs
Explain personnel policies
Secure line of credit
End
None
None
None
None
1
1
5
6, 7
2
3
4
8
11
9, 12
10, 13, 14
16
30
60
18
17
4
12
6
18
20
40
11
14
13
0
19
30
72
27
29
7
15
12
27
35
55
20
23
16
0
28
30
90
30
47
10
18
24
30
50
100
29
26
19
0
Compute the expected time for each activity.
Compute the variance for each activity.
Compute the expected project duration.
What is the probability of completing the project by day 112? Within 116 days?
What is the probability of completing “Negotiate with Unions” by day 90?
3. The expected times and variances for the project activities are given below. What is
the probability of completing the project in 25 periods?
ID
Description
Predecessor
te
Variance
[(b − a)/6]2
1
2
3
4
5
6
7
8
Pilot production
Select channels of distrib.
Develop mktg. program
Test market
Patent
Full production
Ad promotion
Release
None
None
None
1
1
4
3
2, 5, 6, 7
6
7
4
4
10
16
3
2
3
4
2
2
5
10
2
1
Case A7.1
International Capital, Inc.—Part A
International Capital, Inc. (IC), is a small investment banking firm that specializes in securing funds for small- to medium-sized firms. IC is able to use a standardized project format for each engagement. Only activity times and unusual
circumstances change the standard network. Beth Brown has been assigned to this
www.downloadslide.net
246 Chapter 7 Managing Risk
client as project manager partner and has compiled the network information and
activity times for the latest client as follows:
Activity
A
B
C
D
E
F
G
H
I
J
K
Description
Immediate Predecessor
Start story draft using template
Research client firm
Create “due diligence” rough draft
Coordinate needs proposal with client
Estimate future demand and cash flows
Draft future plans for client company
Create and approve legal documents
Integrate all drafts into first-draft proposal
Line up potential sources of capital
Check, approve, and print final legal proposal
Sign contracts and transfer funds
—
—
A, B
C
C
E
C
D, F, G
G, F
H
I, J
Time in Workdays
Activity
Optimistic
Most Likely
Pessimistic
4
2
2
16
6
1
4
2
5
2
17
7
4
5
19
9
7
10
5
8
5
29
10
8
8
28
24
13
28
14
17
8
45
A
B
C
D
E
F
G
H
I
J
K
MANAGERIAL REPORT
Brown and other broker partners have a policy of passing their plan through a project
review committee of colleagues. This committee traditionally checks that all details
are covered, times are realistic, and resources are available. Brown wishes you to
develop a report that presents a planned schedule and expected project completion
time in workdays. Include a project network in your report. The average duration for a
sourcing capital project is 70 workdays. IC partners have agreed it is good business to
set up projects with a 95 percent chance of attaining the plan. How does this project
stack up with the average project? What would the average have to be to ensure a
95 percent chance of completing the project in 70 workdays?
Case A7.2
Advantage Energy Technology Data Center Migration—
Part B
In Chapter 6, Brian Smith, network administrator at Advanced Energy Technology
(AET), was given the responsibility of implementing the migration of a large data
center to a new office location.
www.downloadslide.net
Chapter 7 Managing Risk 247
Time in Workdays
Task Name
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
AET DATA CENTER MIGRATION
Team meeting
Hire contractors
Network design
Ventilation system
Order ventilation system
Install ventilation system
New racks
Order new racks
Install racks
Power supplies and cables
Order power supplies & cables
Install power supplies
Install cables
Renovation of data center
City inspection
Switchover Meetings
Facilities
Operations/systems
Operations/telecommunications
Systems & applications
Customer service
Power check
Install test servers
Management safety check
Primary systems check
Set date for move
Complete move
Optimistic
Dur.
Most Likely
Dur.
Pessimistic
Dur.
54
0.5
6
12
—
18
5
—
13
17
—
6
5
6
19
1
—
7
5
6
7
5
0.5
5
1
1.5
1
1
68
1
7
14
—
21
7
—
14
21
—
7
5
8
20
2
—
8
7
7
7
6
1
7
2
2
1
2
92
1.5
8
16
—
30
9
—
21
25
—
8
11
10
27
3
—
9
9
8
13
13
1.5
9
3
2.5
1
3
Immediate
Predecessor
Critical Path
✓
2
2
—
2
6
—
2
9
—
2
12, 16
12, 16
3, 4
3, 7, 10
—
14
14
14
14
14
13, 14, 15
18, 19, 20, 21, 22, 23
7, 23, 24
25
26
27
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
Careful planning was needed because AET operates in the highly competitive
petroleum industry. AET is one of five national software companies that provide an
accounting and business management package for oil jobbers and gasoline distributors. A few years ago, AET jumped into the “application service provider” world.
Their large data center provides clients with remote access to AET’s complete suite of
application software systems. Traditionally, one of AET’s primary competitive advantages has been the company’s trademark IT reliability. Due to the complexity of this
project, the Executive Committee insisted that preliminary analysis of the anticipated
completion date be conducted.
Brian compiled the following information, in preparation for some PERT analysis:
1. Based on these estimates and the resultant expected project duration of 69 days, the
executive committee wants to know what the probability is of completing the project before a scheduled time (TS) of 68 days.
2. The significance of this project has the executive committee very concerned. The committee has decided that more analysis of the duration of each activity is needed. Prior
to conducting that effort, they asked Brian to calculate what the expected project duration would have to be to ensure a 93 percent chance of completion within 68 days.
www.downloadslide.net
248 Chapter 7 Managing Risk
ADVANTAGE ENERGY TECHNOLOGY (AET)—ACCOUNTS
PAYABLE SYSTEM
The AET sales department has been concerned about a new start-up company that is
about to release an accounts payable system. Their investigation indicates that this new
package will provide features which will seriously compete with AET’s current
Accounts Payable system and in some cases exceed what AET offers.
Tom Wright, senior applications developer at AET, has been given the responsibility of analyzing, designing, developing, and delivering a new accounts payable system
(A/P) for AET customers.
Complicating the issue is the concern of the sales department about AET’s recent
inability to meet promised delivery dates. They have convinced CEO (Larry Martain)
that a significant marketing effort will have to be expended to convince the clients they
should wait for the AET product rather than jump to a package provided by a new
entry to the petroleum software business. Companion to this effort is the importance of
the performance of the software development group.
Consequently, Tom has decided to take the following action: tighten up the estimating effort by his developers; incorporate some new estimating procedures; and use
some PERT techniques to generate probabilities associated with his delivery dates.
Tom’s planning team made a first-cut at the set of activities and associated durations:
Time in Workdays
Task Name
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
ACCOUNTS PAYABLE SYSTEM
Planning meeting
Team assignments
Program specification
Customer requirements
Feasibility study
Systems analysis
Prelim budget & schedule
Functional specification
Prelim design
Configuration & perf needs
Hardware requirements
System specification
Detailed design
Program specification
Programming—first phase
Documentation
Prototype
Development
User testing & feedback
Programming—second phase
Beta testing
Final documentation pkg
Training pkg
Product release
SS = Start to Start lag
Optimistic
Dur.
Most Likely
Dur.
Pessimistic
Dur.
Immediate
Predecessor
1
3
1
4
2
5
8
3
6
1
3
10
3
4
5
12
8
27
14
10
5
8
2
5
12
4
6
7
14
10
32
16
12
7
10
3
7
14
5
8
9
16
12
37
18
3
5
5
7
7
9
10
11
10
12, 13
14
15
10
✓
5
12
10
18
9
4
3
7
14
12
20
10
5
5
9
16
14
22
11
6
7
16
19
16
21
17, 20
21SS, 23
22, 23, 24
✓
✓
2
Critical Path
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
www.downloadslide.net
Chapter 7 Managing Risk 249
3. Based on these estimates and the critical path, the project duration is estimated at
149 days. But an AET salesperson in the Southeast Region has discovered that the
competing A/P package (with significant improvements) is scheduled for delivery
in approximately 145 days. The sales force is very anxious to beat that delivery
time. The executive committee asks Tom for an estimated probability of reducing
his expected project duration by two days.
4. The executive committee is advised by Tom that after all the estimating was completed, he determined that one of his two critical systems analysts might have to
move out of the area for critical family reasons. Tom is still very confident that with
some staff rearrangements, assistance from a subcontractor, and some “hands on”
activities on his part he can still meet the original delivery date, based on 149 days.
This news is very disconcerting to the committee and the sales staff. At this
point, the committee decides that based on the most recent delivery performance of
AET, a modified, comfortable delivery date should be communicated to AET clients—one that Tom and his staff are very likely to meet. Consequently, Tom is
asked to calculate what the expected project duration would have to be to ensure a
98 percent chance of completion within 160 days—that is a “published, drop dead
date” that can be communicated to the clients.