Chapter 13 Progress and Performance Measurement and Evaluation 491
5. Given the following project network, baseline, and status information, develop status reports for periods 1–4 and complete the project summary graph (or a similar
one). Report the final SV, CV, CPI, and PCIB. Based on your data, what is your
assessment of the current status of the project? At completion?
0
1
1
1
2
0
2
0
0
3
2
2
1
1
3
3
2
5
3
3
0
0
3
3
4
4
1
5
2
5
5
0
0
5
5
7
6
0
1
6
LEGEND
0
3
0
0
2
2
2
0
0
2
2
6
ES
5
3
SL
5
LS DUR LF
Baseline budget needs
($ 000)
Total
PV 0
Time period
2
3
4
ACT/
WP
DUR
ES
LF
SL
1
2
0
3
1
12
4
8
2
3
0
3
0
15
3
7
4
4
3
2
0
2
0
8
2
2
5
1
6
EF
0
Schedule information
4
ID
5
2
3
5
0
10
6
3
2
5
0
9
7
1
5
6
0
5
1
5
6
5
3
3
3
6
4
3
3
5
Total PV by period
11
19
11
12
Cumulative PV by period
11
30
41
53 60 65
7
5
SL
www.downloadslide.net
492 Chapter 13 Progress and Performance Measurement and Evaluation
Status Report: Ending Period 1
Task
1
2
3
Cumulative Totals
($000)
%Complete
50%
40%
25%
EV
——
——
——
——
AC
6
8
3
17
PV
4
3
——
——
CV
——
——
——
——
Status Report: Ending Period 2
Task
1
2
3
Cumulative Totals
($000)
%Complete
Finished
80%
75%
EV
——
——
——
——
AC
13
14
8
35
PV
——
——
——
——
CV
——
——
——
——
Status Report: Ending Period 3
Task
1
2
3
4
5
6
Cumulative Totals
%Complete
Finished
80%
Finished
50%
0%
33.3%
EV
12
——
——
——
——
——
——
AC
13
15
10
4
0
4
——
PV
——
——
——
——
——
——
——
CV
——
——
——
——
——
——
——
EV
12
15
——
——
——
——
——
——
Summary Graph
70
60
Index
50
PV
30
20
10
0
0
1
2
3
4
5
Time periods
SV
——
——
——
——
——
——
——
($000)
%Complete
Finished
Finished
Finished
Finished
30%
66.7%
0%
40
SV
——
——
——
——
($000)
Status Report: Ending Period 4
Task
1
2
3
4
5
6
7
Cumulative Totals
SV
——
——
——
——
6
7
8
AC
13
18
10
8
3
8
0
——
PV
——
——
——
——
——
——
——
——
CV
——
——
——
——
——
——
——
——
SV
——
——
——
——
——
——
——
——
www.downloadslide.net
Chapter 13 Progress and Performance Measurement and Evaluation 493
6. The following labor hours data have been collected for a nanotechnology project for
periods 1 through 6. Compute the SV, CV, SPI, and CPI for each period. Plot the
EV and the AC on the summary graph provided (or a similar one). Plot the SPI,
CPI, and PCIB on the index graph provided (or a similar one). What is your assessment of the project at the end of period 6?
2
5
2
4
1
3
7
2
6
2
Legend
4
ES
6
ID
EF
SL
5
LS DUR LF
4
Schedule information
Baseline budget needs–labor hours (00)
Total
PV
ACT/
WP
DUR
1
2
0
2
0
20
2
2
2
7
3
24
16
8
3
6
2
11
3
30
5
5
10
3
2
4
5
2
7
0
25
10
10
2
2
1
5
4
4
11
3
16
4
4
4
6
4
7
11
0
20
7
2
11
13
0
10
ES
LF
SL
SL
1
0
10
2
3
4
Time period
6
7
8
5
9
10
11
12
13
10
5
4
5
Total PV by period
10
10
31
23
16
9
Cumulative PV by period
10
20
51
74
90
99
7
14
5
5
6
6
106 120 125 131
4
4
5
5
5
5
135 140 145
14
www.downloadslide.net
494 Chapter 13 Progress and Performance Measurement and Evaluation
Status Report: Ending Period 1
Task
1
Cumulative Totals
%Complete
50%
EV
——
——
AC
500
500
PV
1000
1000
CV
——
——
SV
——
——
EV
——
——
AC
1500
1500
PV
2000
2000
CV
——
——
SV
——
——
EV
2000
——
——
——
——
AC
1500
0
200
500
2200
PV
2000
——
——
——
——
CV
——
——
——
——
——
SV
——
——
——
——
——
EV
2000
——
——
——
——
AC
1500
1000
800
1500
4800
PV
2000
——
——
——
——
CV
——
——
——
——
——
SV
——
——
——
——
——
EV
2000
——
——
——
——
——
AC
1500
2000
800
1500
400
6200
PV
2000
——
——
——
——
——
CV
——
——
——
——
——
——
SV
——
——
——
——
——
——
EV
2000
——
——
——
——
——
AC
1500
2000
2100
1800
600
8000
PV
2000
——
——
——
——
——
CV
——
——
——
——
——
——
SV
——
——
——
——
——
——
Status Report: Ending Period 2
Task
1
Cumulative Totals
%Complete
Finished
Status Report: Ending Period 3
Task
1
2
3
4
Cumulative Totals
%Complete
Finished
0%
10%
20%
Status Report: Ending Period 4
Task
1
2
3
4
Cumulative Totals
%Complete
Finished
50%
30%
40%
Status Report: Ending Period 5
Task
1
2
3
4
5
Cumulative Totals
%Complete
Finished
Finished
50%
60%
25%
Status Report: Ending Period 6
Task
1
2
3
4
5
Cumulative Totals
%Complete
Finished
Finished
80%
80%
50%
www.downloadslide.net
Chapter 13 Progress and Performance Measurement and Evaluation 495
Period
SPI
CPI
PCIB
1
2
3
4
5
6
——
——
——
——
——
——
——
——
——
——
——
——
——
——
——
——
——
——
SPI = EV/PV
CPI = EV/AC
PCIB = EV/BAC
Indexes Periods 1–6
Summary Graph
2.20
16000
PV
14000
2.00
1.80
1.60
10000
1.40
8000
Index
Labor hours
12000
6000
4000
1.20
1.00
.80
2000
0
.60
0
1
2
3
4
5
6 7 8 9
Time periods
10
11
12 13 14 15
.40
.20
0
0
1
2
3
4
5
Time periods
6
7
www.downloadslide.net
496 Chapter 13 Progress and Performance Measurement and Evaluation
7. The following data have been collected for a British health care IT project for twoweek reporting periods 2 through 12. Compute the SV, CV, SPI, and CPI for each
period. Plot the EV and the AC on the summary graph provided. Plot the SPI, CPI,
and PCIB on the index graph provided. (You may use your own graphs.) What is
your assessment of the project at the end of period 12?
4
2
2
0
1
0
0
4
12
14
2
0
14
6
8
14
3
10
10
0
0
10
10
4
4
0
0
4
4
6
5
4
7
18
4
18
0
14
18
0
0
14
18
8
22
0
22
4
Legend
4
4
2
6
4
8
8
2
2
10
10
6
8
ES
16
ID
EF
2
SL
SL
18
LS DUR LF
Baseline (PV)
($00)
PV
($00) 0
Task
DUR
ES
LF
SL
1
4
0
4
0
8
2
8
4
14
2
40
10
10
10
3
6
4
10
0
30
10
15
5
4
4
4
10
2
20
10
10
5
4
10
14
0
40
6
8
8
18
2
60
7
4
14
18
0
20
8
4
18
22
0
30
2
4
4
6
8
10
12
14
16
18
4
10
20 20
20 20
10
10
10
Period PV total
4
4
30 35 35 50 30 20
Cumulative PV total
4
8
38
10
10
%Complete
50%
20
10
20
10
73 108 158 188 208 218 238 248
Status Report: Ending Period 2
Task
1
Cumulative Totals
20 22
($00)
EV
——
——
AC
4
4
PV
——
——
CV
——
——
SV
——
——
www.downloadslide.net
Chapter 13 Progress and Performance Measurement and Evaluation 497
Status Report: Ending Period 4
Task
1
Cumulative Totals
($00)
%Complete
Finished
EV
——
——
AC
10
10
PV
——
——
CV
——
——
Status Report: Ending Period 6
Task
1
2
3
4
Cumulative Totals
($00)
%Complete
Finished
25%
33%
0%
EV
——
——
——
——
——
AC
10
15
12
0
37
PV
——
——
——
——
——
CV
——
——
——
——
——
Status Report: Ending Period 8
Task
1
2
3
4
Cumulative Totals
EV
——
——
——
——
——
AC
10
20
25
0
55
PV
——
——
——
——
——
CV
——
——
——
——
——
Status Report: Ending Period 10
SV
——
——
——
——
——
($00)
%Complete
Finished
60%
Finished
50%
0%
30%
EV
——
——
——
——
——
——
——
AC
10
30
40
20
0
24
124
PV
——
——
——
——
——
——
——
CV
——
——
——
——
——
——
——
Status Report: Ending Period 12
Task
1
2
3
4
5
6
Cumulative Totals
SV
——
——
——
——
——
($00)
%Complete
Finished
30%
60%
0%
Task
1
2
3
4
5
6
Cumulative Totals
SV
——
——
SV
——
——
——
——
——
——
——
($00)
%Complete
Finished
Finished
Finished
Finished
50%
50%
EV
——
——
——
——
——
——
Period
SPI
CPI
PCIB
2
4
6
8
10
12
——
——
——
——
——
——
——
——
——
——
——
——
——
——
——
——
——
——
AC
10
50
40
40
30
40
210
PV
——
——
——
——
——
——
——
SPI = EV/PV
CPI = EV/AC
PCIB = EV/BAC
CV
——
——
——
——
——
——
——
SV
——
——
——
——
——
——
——