Bạn đang xem bản rút gọn của tài liệu. Xem và tải ngay bản đầy đủ của tài liệu tại đây (6.01 MB, 483 trang )
340
Electrical Power Systems
generation on the same footing as the IPPs. Figure 13.2 shows the deregulated utility structure.
In Fig. 13.2, GENCOs which will compete in a free market to sell electricity they produce. It can
be assumed that the retail customer will continue for some time to buy from the local distribution
company. Such distribution companies have been designated as DISCOs. The entities that will
wheel this power between GENCOs and DISCOs have been designated as TRANSCOs. Although
it is conceptually clean to have separate functionalities for the GENCOs, TRANSCOs and
DISCOs, in reality there will exist companies with combined or partial responsibilities.
Fig. 13.2: Deregulated utility structure.
With the emergence of the distinct identities of GENCOs, TRANSCOs, DISCOs and the
ISO, many of the ancillary services of a VIU will have a different role to play and hence have
to be modeled differently. Among these ancillary services is the Automatic Generation Control
(AGC). In the new scenario, a DISCO can contract individually with a GENCO for power and
these transactions will be made under the supervision of ISO.
13.2 TRADITIONAL VS RESTRUCTURED SCENARIO
In the previous section vertically integrated utility (VIU) structure and deregulated utility
structure have been discussed. As there are several GENCOs and DISCOs in the deregulated
structure, a DISCO has the freedom to have a contract with any GENCO for transaction of
power. A DISCO may have a contract with a GENCO in another control area. Such transactions
are called bilateral transactions. All the transactions have to be cleared through an impartial
entity called an independent system operator (ISO). The ISO has to control a number of socalled ancillary services, one of which is AGC.
13.3 DISCO PARTICIPATION MATRIX (DPM)
In the restructured environment, GENCOs sell power to various DISCOs at competitive prices.
Thus, DISCOs have the liberty to choose the GENCOs for contracts. They may or may not have
contracts with the GENCOs in their own area. This makes various combinations of GENCODISCO contracts possible in practice.
We will describe here DISCO participation matrix (DPM) to make the visualization of
contracts easier. DPM is a matrix with the number of rows equal to the number of GENCOs and
the number of columns equal to the number of DISCOs in the system. For the purpose of
Automatic Generation Control in a Restructured Power System 341
explanation, consider a two-area system in which each area has two GENCOs and two DISCOs
in it. Let GENCO1, GENCO2, DISCO1 and DISCO2 are in area-1, and GENCO3, GENCO4,
DISCO3 and DISCO4 are in area-2 as shown in Fig. 13.3.
Fig. 13.3: Schematic of a two-area system in a restructured power system.
The DPM of Fig. 13.3 can be given as:
DISCO1
DISCO3
DISCO4
GENCO1
DPM =
DISCO2
cpf 11
cpf 12
cpf 13
cpf 14
GENCO2
cpf 21
cpf 22
cpf 23
cpf 24
GENCO3
cpf 31
cpf 32
cpf 33
cpf 34
GENCO4
cpf 41
cpf 42
cpf 43
...(13.1)
cpf 44
Each entry in eqn. (13.1) can be thought of as a fraction of a total load contracted by a
DISCO (column) toward a GENCO (row). Thus, the ij-th entry corresponds to the fraction of the
total load power contracted by DISCO j from a GENCO i. The sum of all the entries in a column
in this matrix is unity. DPM shows the participation of a DISCO in a contract with a GENCO,
and hence the DISCO participation matrix. In eqn. (13.1) , cpfij refers to contract participation
factor. For the purpose of explanation, suppose that DISCO2 demands 0.1 pu MW power, out
of which 0.02 pu MW is demanded from GENCO1, 0.035 pu MW demanded from GENCO2,
0.025 pu MW demanded from GENCO3 and 0.02 pu MW demanded from GENCO4.
The column 2 entries in eqn. (13.1) can easily be defined as:
cpf12 =
0.02
= 0.20;
0.1
cpf32 =
0.025
0.02
= 0.25; cpf42 =
= 0.20;
0.1
0.1
cpf22 =
0.035
= 0.35;
0.1
Note that cpf12 + cpf22 + cpf32 + cpf42 = 1.0
Other cpfs are defined easily to obtain the entire DPM. In general
åi cpf ij
= 1.0
...(13.2)
13.4 BLOCK DIAGRAM REPRESENTATION
In chapter-12, Block diagram representation of two area system has been presented for
conventional AGC. Here, we will formulate the block diagram for a two area AGC system in the
342
Electrical Power Systems
deregulated scenario. Whenever a load demanded by a DISCO changes, it is reflected as a local
load in the area to which this DISCO belongs. This corresponds to the local loads DPL1 and DPL2
and should be reflected in the deregulated AGC system block diagram at the point of input to
the power system block. As there are many GENCOs in each area, ACE signal has to be
distributed among them in proportion to their participation in AGC. Coefficients that distribute
ACE to several GENCOs are termed as ACE participation factors.
Note that
NGENCO j
¢
å a ji
= 1.0
...(13.3)
i=1
Where
¢
a ji = participation factor of i-th GENCO in j-th area
NGENCOj = Number of GENCOs in j-th area.
Unlike the traditional AGC system, a DISCO asks/demands a particular GENCO or GENCOs
for load power. These demands must be reflected in the dynamics of the system. Turbine and
governor units must respond to this power demand. Thus, as a particular set of GENCOs are
supposed to follow the load demanded by a DISCO, information signals must flow from a
DISCO to a particular GENCO specifying corresponding demands. The demands are specified
by cpfs (elements of DPM) and the pu MW load of a DISCO. These signals carry information as
to which GENCO has to follow a load demanded by which DISCO.
The scheduled steady state power flow on the tie-line is given as:
scheduled =
DPtie 12
\
(Demand of DISCOs in area-2 from GENCOs in area-1)
(Demand of DISCOs in area-1 from GENCOs in area-2)
2
4
S cpf ij
scheduled = S
DPtie 12
i =1 j=3
4
DPL j S
2
S cpfij DPL j
i =3 j=1
...(13.4)
error
At any given time, the tie-line power error DPtie,12 is defined as:
error
actual
scheduled
DPtie 12 = DPtie 12 DPtie 12
...(13.5)
error
DPtie 12 vanishes in the steady-state as the actual tie-line power flow reaches the scheduled
power flow. This error signal is used to generate the respective ACE signals as in the traditional
scenario:
error
ACE1 = B1 D F1 + DPtie 12
...(13.6)
error
ACE2 = B2 D F2 + a12 DPtie 12
...(13.7)
For two area system as shown in Fig. 13.3, contracted power supplied by i-th GENCO is
given as:
NDISCO=4
DP i =
å cpfijDPLj
j=1
...(13.8)
Automatic Generation Control in a Restructured Power System 343
The block diagram of two area AGC system in a deregulated environment is shown in Fig.
13.4(a). Simplified version of Fig. 13.4(a) is shown in Fig. 13.4(b). In fig. 13.4(b), for i = 1,
...(13.9)
D P1 = cpf11 D PL1 + cpf12 D PL2 + cpf13 D PL3 + cpf14 D PL4
Fig. 13.4(=): Block diagram of two-area deregulated power system.
344
Electrical Power Systems
Fig. 13.4(>): Simplified representation of fig. 13.4(a).
Automatic Generation Control in a Restructured Power System 345
Similarly, DP2, DP3 and DP4 can easily be obtained from eqn. (13.8). In Fig. 13.4(b), DPuc1 and
DPuc2 are uncontracted power demand (if any).
Also note that DPL1,LOC = DPL1 + DPL2 and DPL2,LOC = DPL3 + DPL4. In the proposed AGC
implementation, contracted load is fed forward through the DPM matrix to GENCO setpoints.
This is shown in Fig. 13.4(b) i.e., DP1, DP2, DP3 and DP4. The actual loads affect system dynamics
via the inputs DPL,LOC to the power system blocks. Any mismatch between actual and contracted
demands will result in a frequency deviation that will result in a frequency deviation that will
¢
¢
¢
drive AGC to redispatch GENCOs according to ACE participation factors, i.e., a11 , a12 , a21 ,
and a22 . The AGC scheme does not require measurement of actual loads. The inputs DPL1,LOC
¢
and DPL2,LOC in the block diagram of Fig. 13.4 (a) & (b) are part of the power system model, not
part of AGC.
13.5 STATE SPACE REPRESENTATION OF THE TWO-AREA SYSTEM
IN DEREGULATED ENVIRONMENT
The closed loop system shown in Fig. 13.4 (b) is characterized in state space form as
X = AX + BU + GP + g p
...(13.10)
For this case, A is 11 × 11 matrix, B is 11 × 2 matrix, G is 11 ´ 4 matrix and g is 11 × 2 matrix.
Details of this matrices are given below:
LM 1
MM T
MM 0
MM 2pT
MM 0
MM 1
MM R T
0
A = M
MM 1
MM R T
MM 0
MM 0
MM
MM 0
MM 0
N
p1
12
1 g1
2 g2
0
1
Tp2
2 pT12
K p1
K p1
Tp1
K p2 a12
Tp1
Tp2
0
0
K p1
Tp1
0
0
K p2
0
0
0
K p2
0
0
0
0
0
1
Tt1
1
T g1
0
0
Tp2
0
0
Tp2
0
0
0
0
0
0
0
0
0
0
0
1
Tt2
1
Tg2
0
0
0
0
0
0
1
Tt3
1
Tg3
0
0
0
1
Tt1
0
0
0
0
0
0
0
1
Tt2
0
0
0
0
0
0
0
0
0
0
0
1
R3 Tg3
1
Tt3
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
R4 Tg4
1
Tt4
0
0
0
0
0
0
0
0
0
0
OP
PP
0 P
P
0 P
P
0 P
PP
0 P
PP
0 P
PP
0
PP
0 P
PP
0 P
P
1 P
P
T P
1 P
P
T Q
0
t4
g4
346
Electrical Power Systems
LM 0
MM 0
MM 0
0
a
MMT¢
MM 0
a
MMT¢
MM 0
MM 0
MM 0
MNM 0
11
g1
B=
12
g2
LM -K
0 O
P MM T
0 P
0
0 P
PP MMM 0
0
0 P
0
PP MMM cpf
0 P
MT
, G= M
0 P
0
PP MM cpf
0
T
a¢ P
PP MMM cpf
0
T
0 P
PP MMM T0
a¢
T Q
P MM cpf
MN T
- K p1
p1
Tp1
p1
0
0
0
cpf12
Tg1
0
cpf22
Tg2
0
cpf32
Tg3
0
cpf42
Tg4
11
g1
21
21
g3
22
g4
g2
31
g3
41
g4
LMu OP
U = M P,
NMu QP
1
2
0
0
- K p2
- K p2
Tp2
0
0
cpf13
Tg1
0
cpf23
Tg2
0
cpf33
Tg3
0
cpf43
Tg4
Tp2
0
0
cpf14
Tg1
0
cpf24
Tg2
0
cpf34
Tg3
0
cpf44
Tg4
LMDPL OP
DPL P
P= M
MMDPL PP
NDPL Q
OP LM -K
PP MM T
PP MM 0
PP MM 0
PP MM 0
PP g = MM 0
PP MM 0
PP MM 0
PP MM 0
PP MM 0
PP MM 0
PQ MN 0
1
2
3
p1
p1
LMDP
MNMDP
uc1
and p =
uc2
4
0
- K p2
Tp2
0
0
0
0
0
0
0
0
0
OP
PP
PP
PP
PP
PP
PP
PP
PP
PP
PP
PQ
OP
PQP
Integral control law for area-1 and area-2 are given as:
z
z
U1 = K I1 ACE1dt
...(13.11)
U2 = K I2 ACE2 dt
...(13.12)
KI1 and KI2 are the integral gain settings of area-1 and area-2 respectively,
Case-1
Consider a case where the GENCOs in each area participate equally in AGC, i.e., ACE
participation factors are a11 = 0.5, a12 = 1 a11 = 0.5; a21 = 0.5, a22 = 1 a21 = 0.50. Assuming
¢
¢
¢
¢
¢
¢
that the load change occurs only in area-1. Thus, the load is demanded only by DISCO1 and
DISCO2. Let the value of this load demand be 0.04 pu MW for each of them, i.e., DPL1 = 0.04
pu MW, DPL2 = 0.04 pu MW, DPL3 = DPL4 = 0.0. DISCO participation matrix (DPM), referring
to eqn. (13.1) is considered as
LM0.50
0.50
DPM = M
MM 0
N0
0.50
0.50
0
0
0
0
0
0
0
0
0
0
OP
PP
PQ
Automatic Generation Control in a Restructured Power System 347
Note that DISCO3 and DISCO4 do not demand power from any GENCOs and hence the
corresponding contract participation factors (columns 3 and 4) are zero . DISCO1 and DISCO2
demand identically from their local GENCOs, viz., GENCO1 and GENCO2. Therefore, cpf11 =
cpf12 = 0.50 and cpf21 = cpf22 = 0.50.
Fig. 13.5(=): D.1 (Hz) vs. time(sec).
Fig. 13.5(>): D.2 (Hz) vs. time (sec).
Fig. 13.5(?): D2tiel2act (pu Mw) vs. time (sec).
348
Electrical Power Systems
Fig. 13.5(@): D2tiel2error (pu Mw) vs. time (sec).
Fig. 13.5(A): D2g1 (pu Mw) vs. time (sec).
Fig. 13.5(B): D2g2 (pu Mw) vs. time (sec).
Fig. 13.5(C): D2g3 (pu Mw) vs. time (sec).
Automatic Generation Control in a Restructured Power System 349
Fig. 13.5(D): D2g4 (pu Mw) vs. time (sec).
Fig. 13.5: Dynamic responses for Case-1.
Figure 13.5 shows the results of this load change: area frequency deviations, actual power
flow on the tie-line ( in a direction from area-1 to area-2), and the generated powers of various
GENCOs, following a step change in the load demands of DISCO1 and DISCO2.
The frequency deviation in each area goes to zero in the steady state. Since, there are no
contracts of power between a GENCO in one area and a DISCO in another area, the scheduled
steady state power flow over the tie-line is zero.
In the steady state, generation of a GENCO must match the demand of the DISCOs in
contract with it. Expanding eqn. (13.8), we have,
DPi = cpf i1 DPL1 + cpf i2 DPL2 + cpf i3 DPL3 + cpf i4 DPL4
...(13.13)
For the case under consideration, we have,
DPg1,steady-state = DP1 = 0.5 ´ 0.04 + 0.50 ´ 0.04 = 0.04 pu MW.
Similarly
DPg2,steady-state = DP2 = 0.04 pu MW
DPg3,steady-state = DP3 = 0.0 pu MW
DPg4,steady-state = DP4 = 0.0 pu MW
Figure 13.5 also shows the actual generated powers of the GENCOs reach the desired
values in the steady state GENCO3 and GENCO4 are not contracted by any DISCO for a
transaction of power, hence, their change in generated power is zero in the steady-state, i.e.,
DPg3,steady-state = 0.0 pu MW and DPg4,steady-state = 0.0 pu MW.
Case-2
Here we will consider that all the DISCOs have contract with the GENCOs for power as per the
following DISCO participation Matrix (DPM):
LM0.50
0.20
DPM = M
MM 0.0
N0.30
0.25
0.25
0.25
0.25
0.0
0.0
10
.
0.0
0.30
0.0
0.70
0.0
OP
PP
PQ
350
Electrical Power Systems
In this case, it is also assumed that each DISCO demands 0.04 pu MW power from GENCOs
as defined by cpfs in DPM matrix and each GENCO participates in AGC as defined by following:
apfs: a11 = 0.75, a12 = 0.25; a21 = a22 = 0.50
¢
¢
¢
¢
Note that ACE participation factors (apfs) affect only the transient behaviour of the
system and not the steady-state behaviour when uncontracted loads are absent, i.e.,
DPuc1 = DPuc2 = 0.0.
The scheduled power flow on the tie-line in the direction from area-1 to area-2 is (eqn. 13.4):
scheduled
DPtie,1-2
2
4
4
2
i=1
=
j= 3
i =3
j=1
å å cpfijDPL j å å cpfijDPLj
Fig. 13.6(=): D.1(Hz) vs. time (sec).
Fig. 13.6(>): D.2(Hz) vs. time (sec).
Fig. 13.6(?): D2tiel2, actual (pu Mw) vs. time (sec).